On a multi-pour project, the most expensive formwork is the formwork standing idle under a curing slab. Early striking is the technique that releases most of it days earlier — without disturbing the concrete.
In a drophead system, every prop or cuplock jack carries a quick-action drophead with two positions — up and down. Strike the drophead wedge and the primary beams drop about 115 mm, while the drophead itself keeps supporting the concrete soffit through the plywood contact point.
That 115 mm is exactly enough clearance to remove the infill beams and primary beams — while the slab above remains supported and completely undisturbed through its curing period.

Our quick-action dropheads are rated to a maximum axial load of 40 kN and fit standard props or cuplock adaptors. Whether early striking is right for your slab depends on the concrete design strength and your engineer's striking criteria — but where it fits, it routinely cuts the formwork stock a project has to rent or buy.